Project Details
SCOPE OF WORKS:
- Enabling Works
- Reduced Level Excavation
- Pile Mat
- Piling Attendance
- Underpinning
- Foundations
- Drainage
- Service Ducts
- 2 x Reinforced Concrete Frames (9 floors)
KEY QUANTS:
- Excavation: 2,500 m3
- Concrete: 5,450 m3
- Reinforcement: 850 tons
- Formwork: 19,400 m2