Project Details
SCOPE OF WORKS:
- Enabling Works
- Reduced Level Excavation
- Pile Mat
- Piling Attendance
- Retaining Walls
- Foundations
- Drainage
- Service Ducts
- Reinforced Concrete Frame (5 floors)
Key Quants:
- Excavation: 1,400 m3
- Concrete: 2,170 m3
- Reinforcement: 380 ton
- Formwork: 8,350 m2