Project Details
Scope of Works:
- Piling Attendance
- Capping Beam
- Temporary Propping (4 Levels)
- Top-Down Logistics Slab
- Bulk Excavation
- Foundations
- Drainage
- Reinforced Concrete Basement (3 Floors)
- Reinforced Concrete Frame (7 Floors)
Key Quants:
- Excavation: 11,500 m3
- Concrete: 4,100 m3
- Reinforcement: 1,400 tons
- Formwork: 13,650 m2