Project Details
Scope of Works:
- Enabling Works
- Pile Mat
- Piling Attendance
- Bulk Excavation
- Foundations
- Drainage
- Service Ducts
- Reinforced Concrete Basement
- Reinforced Concrete Frames (8 floors)
Key Quants:
- Excavation: 20,050 m3
- Concrete: 12,230 m3
- Reinforcement: 2,090 tons
- Formwork: 39,280 m2