St Albans

Project Details

Client: James Taylor Construction
Contract Value: £6.5 million
Address: 63 Campfield Road, St. Albans, AL1 5HT
Programme: 68 weeks

Scope of Works:

  • Enabling Works
  • Pile Mat
  • Piling Attendance
  • Capping Beam
  • Bulk Excavation
  • Foundations
  • Drainage
  • Service Ducts
  • Reinforced Concrete Basement
  • Reinforced Concrete Frame (5 Floors)

Key Quants:

  • Excavation: 24,500 m3
  • Concrete: 5,700 m3
  • Reinforcement: 1,150 tons
  • Formwork: 20,500 m2